Licence number: 10801
Annual Return Start: 01 Jul 2008
Annual Return End: 30 Jun 2009
Date Received: 27 Aug 2009
 
Licence Condition numberType of non-complianceEPA actionsNo. of times occurred
M2 Due to a monitoring oversight, quarterly groundwater samples as EMP's 3-10 were not analysed for total phosporus throughout the Monitoring Period. Reactive Phosphorus was used as an accurate surrogate in this instance. Appropriate Action taken by licensee 1
M2 Due to the motor of the groundwater sampling pump burning out, standing water levels for the month of February 2009 could not be collected at piezometers 200 (EMP 3) and 205 (EMP 4). Appropriate Action taken by licensee 1
M2 Due to access being prohibited by irrigation events, standing water level measurements at the following piezometers could not be taken at piezometer 205 (EMP 4) during the months of August and October 2008. EPA to monitor future compliance with this condition 1
M2 Due to access being prohibited by irrigation events, the August and October 2008 quarterly samples could not be collected from piezometer 205 (EMP 4). EPA to monitor future compliance with this condition 1